A Summary is provided on a single page which contains the roll-up of the individual cost items
developed in detail...

The table below outlines the basics of the Summary Page:
Comments or feedback regarding this website? contact webmaster@gmpcompliancebasis.com
Copyright 2004-08
Industry Links
Compliance Basis
ROM Cost Model
GMP
GMP Compliance Basis
GMP CB Blog
cGMP Compliance...How much will it cost?...
Regulated Facilities
and Processes
Engineering
Project Management
Commissioning
Qualification
Cost...always a critical part of project planning and execution...

The building, the equipment, services escalation, Owner internal costs...all must be considered
in order to establish a budget for the Probable Cost of a project...

Please review the ROM Cost Model below for additional information...

Remember to consult with a qualified industry professional if you have further questions...

The Total Installed Cost is noted at the bottom of the Summary page example...
Take our Industry Survey
Home
Operating System Description
Checklists
Tools
Contact GMP CB
Direct Costs
Direct Costs are items that result in a physical assest...a building, a process skid, etc...

In this example, they are broken up by floor and classification for the facility, and by process
equipment and installation on the process side...
GMP Compliance
Basis Blog
Click here
Q8 Design Space
"V" Model
All Rights Reserved
Future
Legal Disclaimer
About GMP CB
Home
Summary
Our advertisers
Page Links
Explanation
OS - Engineering
OS - Validation
OS - Construction
Other factors impact the total cost of a project and these items should be estimated at a project
level...

This example includes a project contingency and escalation...
Other Project Costs
Indirect Costs
Indirect costs are project expenses for other items like fees for professional services required
to execute the project

In this example, there are costs for engineering, construction management, validation, and
miscellaneous

Indirect costs can also be captured to cover internal Owner costs required to support the
project...

Other items in this part of the table could include furniture and computer network installation
which are typically paid by the Owner but may not be counted directly as part of the capital
project costs...
The individual cost items shown above are built up as noted in the following tables...

Obviously, this method lends itself to a spreadsheet analysis for developing individual cost
items and rolling them forward to a summary page...

The actual spreadsheet will be posted shortly...
ROM Opinion of Probable Cost
Summary Page
 
Project:
Project Name
Location:
Project Location
Client:
Client Organization
 
Direct Costs
  Construction Cost
Remarks
Facility
$13,625,000
 
Equipment
$15,391,000
 
 
Indirect Costs
Services
$6,500,000
 
Owner Costs
$870,000
 
 
Other Project Costs
 
Contingency
$2,920,000
 
Escalation
$1,160,000
 
 
Total Installed Cost
$40,466,000
 
 
Direct Costs
 
Facility
 
Non-Process Space
Area
(GSF)
Average Unit Price per
SF
Construction Cost
Remarks
First Floor
24,600
$200
$4,920,000
 
Second Floor
20,500
$161
$3,310,000
 
Third Floor
12,450
$199
$2,475,000
 
         
    Subtotal
$10,705,000
 
 
Process Space
       
First Floor
4,300
$200
$860,000
 
Second Floor
4,300
$479
$2,060,000
 
Third Floor
0
$0
$0
 
 
    Subtotal
$3,625,000
 
         
Equipment
    Quantity
Cost
 
Procurement
  8
$6,156,750
 
Installation
  Lump Sum
$9,235,125
 
 
    Subtotal
$15,391,875
 
         
Subtotal-
Direct Costs
    $29,016,875
 
         
Indirect Costs
 
Services
 
  Service
Percentage
Cost
Remarks
  Engineering
10 %
$2,920,000
 
  Construction Management
4 %
$1,160,000
 
  Procurement
2 %
$580,000
 
  Commissioning
2 %
$580,000
 
  Validation
4 %
$1,160,000
 
  Other
LS
$100,000
 
 
    Subtotal
$6,500,000
 
         
Owner Costs
  Service
Percentage
Cost
Remarks
  Project Management
1 %
$290,000
 
  Engineering
1 %
$290,000
 
  Support
1 %
$290,000
 
 
    Subtotal
$870,000
 
         
Subtotal-
Indirect Costs
    $7,270,000
 
         
Other Project Costs
 
  Item
Percentage
Cost
Remarks
  Contingency
10 %
$2,920,000
 
  Escalation
1 %
$1,160,000
 
 
Subtotal-
Other Costs
    $4,080,000